In this lesson
- Draw DC and AC routes in different styles: DC from panels is live in daylight.
- Show every isolator, the generation meter and the second-supply labels.
- Batteries stay out of sleeping rooms and escape routes.
Solar panels and batteries add a second source of power. The plan has to show where it comes from, how it is switched off and where the battery can safely live.
What to draw
- The array, as a note if it is on the roof, and the DC route to the inverter.
- The inverter with its DC isolator, and the AC route through an AC isolator to the board.
- The generation meter, export limiting if used, and warning labels at the board and meter.
- The battery, its location and its fire separation.
Connection rules
In the UK, systems up to 16 A per phase usually follow G98: install, then notify within 28 days. Larger ones follow G99 and need approval first. In the US, rooftop PV needs rapid shutdown under NEC 690.12.
Try it
Sort the battery locations above into suitable and unsuitable.
Check your understanding