Module 2 · Distribution and layout · Lesson 7 of 11

Multi-storey plans, risers and fire stopping

Free advanced lesson: plan electrics across floors with one sheet per floor, risers and sub-mains, boards per floor and fire stopping at every penetration.

8 min · 0 XP · 0 of 11 lessons done

Lesson 7 of 11 All lessons
  1. 1Maximum demand and diversity
  2. 2Cable sizing and correction factors
  3. 3Fault protection, Zs and disconnection times
  4. 4US load calculations and wire sizing
  5. 5Three-phase supplies and load balancing
  6. 6Sub-mains and distribution boards
  7. 7Multi-storey plans, risers and fire stopping
  8. 8Solar PV and battery storage on the plan
  9. 9Data, alarm and power segregation
  10. 10Inspection records on plans
  11. 11Final test: advanced electrical floor plans

In this lesson

  • One sheet per floor, at the same scale and orientation.
  • Vertical routes go through a planned riser or a few defined points.
  • Every penetration through a fire-resisting floor or wall must be sealed.

On one floor, every cable is on one sheet. Add floors and the plan needs a system: a sheet per floor, a clear riser and markers that link the sheets.

MULTI-STOREYRisers, boards and fire stopping Ground floor First floor Second floor Riser DB-G DB-1 DB-2 Intake and main Sub-mains to each floor Fire stoppingat every floor One boardper floor, labelled Plan markerspair each floor's sheet
A section through three floors: sub-mains in a riser, a board per floor, fire stopping at each floor.

A sheet per floor

Keep the same scale and orientation on every floor. A riser then sits in the same place on each sheet, and a reader finds vertical routes instantly.

Risers and boards

In flats and commercial buildings, sub-mains rise in a shaft to a board on each floor or in each unit. In houses, vertical runs follow a stud wall, a boxed pipe run or the airing cupboard.

Fire stopping and support

Seal every hole a cable makes through a fire-resisting floor or wall, and mark it on the plan so it can be checked. Support long vertical runs so their weight does not strain the terminations.

Try it

Place the fire-stopping seals on the section drawing above.

Check your understanding

Official documents and further reading

Progress is saved in this browser.

Go deeper: related guides

Electricians Loft Conversion Electrical Plan: What You Need Plan loft conversion electrics: new lighting and socket circuits, an en-suite, two-way landing lights and mains smoke alarms interlinked with the floor below. 3 min read Electricians How to Plan a House Rewire, Step by Step Plan a full house rewire in eight steps: survey, agree points, design circuits, plan routes, first fix, plaster, second fix and certification. 3 min read