- Zs = Ze + (R1 + R2). Lower Zs means more fault current and a faster trip.
- The maximum Zs is set by the current that trips the breaker instantly: 5 × In for type B, 10 × In for type C.
- Long runs and small cables raise Zs, so check it at the design stage.
If a line conductor touches earthed metal, the protective device must switch off before anyone gets a dangerous shock. Whether it can depends on the earth fault loop impedance, Zs.
The loop
Fault current flows out along the line conductor, back along the protective conductor and through the supply. Zs is the impedance of that whole loop: Ze from the supply plus R1 + R2 from the circuit.
Breaker types
A type B breaker trips instantly somewhere between 3 and 5 times its rating, a type C between 5 and 10 times. To be sure, the fault current must reach the top of that band. That is why a C32 allows only half the Zs of a B32.
Design it in
R1 + R2 grows with length and shrinks with conductor size. Read the route length from the plan, estimate Zs before you install, and choose a larger cable or a shorter route if it is too high.
Try it
In the gauge, find the longest 2.5 mm² run a B32 allows on a TN-C-S supply, then switch to a C32 and see what changes.