In this lesson
- Most circuits on a three-phase board are single phase, so you choose each one's phase.
- Balanced phases cancel in the neutral; unbalanced ones load it.
- Place the biggest loads first, then fill the lightest phase.
Larger homes, workshops and small commercial units often have a three-phase supply. The designer decides which phase every single-phase circuit uses, and that decision shows on the plan and the schedule.
Why it matters
- Each phase has its own fuse. One overloaded phase can blow while the others sit idle.
- Balanced loads cancel in the neutral. Unbalanced ones make it carry current.
- A heavily loaded phase drops more voltage.
A simple method
- List every circuit with its demand after diversity.
- Place the biggest single-phase loads first, one per phase.
- Add each remaining circuit to the lightest phase.
On the plan
Add the phase to each circuit's label, for example "C4 Kitchen ring, L2". Three-phase equipment, such as a 22 kW EV charger, loads all phases equally and needs no balancing.
Try it
Balance the board above so the three phases are within a few amps of each other.